Crane Load Chart Verification Checklist
A load chart is only valid for the crane configuration and conditions to which it applies. Use this checklist when selecting a chart and preparing a lift review.
A review aid, not a lift approval
This general checklist does not replace the manufacturer's operating manual, site-specific engineered lift plan or competent-person approval. Always apply the exact machine documentation and local lifting procedures.
Six checks before relying on a load chart
Work through these checks in order. A mismatch at any point means the selected rating may not apply.
- 01
Confirm the exact crane and document
Check the manufacturer, model designation, applicable variant and the document edition against the equipment and its approved operating manual. Similar model names do not guarantee interchangeable load charts.
- Is this the correct crane variant?
- Is the chart edition applicable to this machine?
- 02
Match the rigged configuration
Confirm main boom length, jib or luffing attachment, counterweight, outrigger position or crawler setup, and any specified superlift arrangement. Use only the chart tables and notes for the actual configuration.
- Are the installed counterweights and attachments represented?
- Does the support configuration match the chosen table?
- 03
Establish the maximum working radius
Working radius is measured horizontally from the crane centre of rotation to the load line. Verify the maximum radius during the lift, not only at pickup. Boom deflection and the planned lift path may change the operating radius.
- Have pickup, travel/slew and placement positions been considered?
- Is the radius measured from the correct reference point?
- 04
Read the correct capacity and notes
Use the chart for the relevant boom length, radius, working sector and operating condition. Check every applicable note, limitation and footnote. Do not interpolate between values unless the manufacturer explicitly permits it.
- Is the lifting sector correct?
- Are special deratings or restrictions applicable?
- 05
Confirm gross versus net load
Check how the manufacturer defines the published rating. Account for the lifted item and all applicable hook blocks, lifting beams, shackles, slings, attachments and other below-hook equipment. Never assume the chart value is the allowable payload.
- Are all accessory weights known?
- Does the remaining allowable payload meet the lift requirement?
- 06
Check the complete lift conditions
Verify hoist line pull, reeving, ground support and levelness, operating wind limits, lifting over different sectors, any pick-and-carry restrictions, and site hazards. A published capacity does not by itself validate the overall lifting operation.
- Are all chart assumptions met on site?
- Have ground-bearing and environmental limits been reviewed?
What to record for the lift review
Record the crane model, chart revision, selected configuration and table, operating sector, maximum working radius, rated capacity, accessory deductions, proposed gross load and the controlling notes. Keep the relevant manufacturer chart with the lift plan.
A large nominal crane rating is not proof that a particular lift is feasible. Capacity depends on the operating setup and the most demanding position in the planned lift sequence.