Working Radius in Crane Load Charts: Pickup, Slew and Placement
Understand why a crane lift must be checked at the most demanding radius, not just the pickup point, with practical field verification steps.
A crane's working radius is the horizontal distance from its centre of rotation to the vertical line through the hook or suspended load. Radius is not the same as boom length, and it is not the horizontal distance from the front bumper or the nearest outrigger. The correct reference point matters because published load capacities are organised around the geometry of the crane.
Many lift plans show the pickup radius but omit the placement radius or the route between them. That can overlook a controlling configuration, particularly when a load is slewed around equipment or lowered beyond an obstruction. A lift cannot be evaluated from one convenient point alone.
Step 1
Measure the correct radius
Start with the centre of slew or other manufacturer-defined centre of rotation. Determine the horizontal distance to the centreline of the suspended hook; verify the applicable definition in that crane's manual. When measuring from the edge of a structure or the crane carrier, correct the dimensions back to the rotation centre.
Do not confuse an offset in a plan drawing with a radius: two perpendicular offsets must be combined geometrically to obtain the straight-line horizontal distance. In a top view, the hook line and the rotation centre are what matter, not the actual path along the ground.
Items to verify
- Use a site survey or dimensioned lifting sketch.
- Identify the crane rotation centre and the load centreline.
- Keep all radius dimensions in the same unit as the load chart.
Step 2
Check the complete lift path
Plot pickup, any planned slew or relocation, and final placement. For a stationary crane, the horizontal radius can vary because the hook line does not always describe a perfect circle during simultaneous boom luffing and hoisting. If the boom has to be lowered to clear an obstruction, the largest radius may occur during that manoeuvre.
Clearance to a pipe rack, neighbouring structure or an installed module is a separate condition from lifting capacity. A clear geometric path does not prove sufficient rated capacity, and a compliant capacity does not prove collision-free movement.
Items to verify
- Record both pickup and set-down radii.
- Identify the maximum radius anywhere in the planned motion.
- Review clearance and operating sector at the same points.
Step 3
Allow for the actual loaded condition
A sketch based on unloaded boom geometry is an approximation. Boom deflection under load and changes in hook position may affect the operating radius. Consult the official manufacturer procedure, the crane indicators and the site measurement method appropriate for the lift.
Do not interpolate or select an in-between row because the chart contains a nearby value. Follow the manufacturer's stated rules for radius and boom-length selection, including any restrictions on selecting intermediate configurations.
Items to verify
- Compare measured or manufacturer-calculated radius with the chart table.
- Account for any operating limits and chart notes.
- Have the chosen lift geometry reviewed against the actual crane configuration.
Step 4
A simple planning illustration
Suppose a conceptual layout has a pickup at 12 m radius and a placement at 18 m radius, with a required change in boom angle between them. These are illustrative distances, not data for a specific crane. A planner who checks only the 12 m row has not established the capacity available at 18 m.
The correct next step is to use the applicable manufacturer chart for the crane's actual configuration and verify the most demanding point, including the changes to boom length, attachment and operating sector. The illustration is not a capacity recommendation.
Items to verify
- Do not use the nominal crane capacity as a substitute for a radius-specific rating.
- Document the controlling radius in the lift review.